This announcement has been published to notify you of a planned hardware maintenance that will be performed for SV202 server at the following date and time :

Friday, December 21st between 11:00 PM to  3:00AM

You should make sure that any unsaved work is saved prior to 9PM. 

In this maintenance  we will

  • replace 480GB ssd disks with 2X 960GB intel DC4500s SSDs
  • Add Hardware Raid card with BBU 
  • Building RAID 1 Array

Planned TimeFrame [Updated]

  • AT 11PM we will shutdown the server.
  • AT 2 AM We will restore power to the server
  • AT 2:30 AM Monitoring Hardware and software 
  • AT 2.45 AM add the network connectivity to the server

We apologize if this maintenance make any inconvenience for your work. We took this time frame due to low traffic and make minimum impact for your work.

 

 